Client
Borough of Telford & Wrekin
Location
Telford and Wrekin
Value
£10m+
Duration
82 weeks
Live – Ercall Wood Academy
This project will see a new three-storey science block building, a single-storey dining hall extension and internal refurbishments to ground floor classrooms and staircase areas.
Start date – 24th March 2024
April & May – Complete site setup and commencement of groundworks for the three-storey science block. Started work to the retaining wall, and the footings.
July & August – Steel frame erected for the three-storey block, along with concrete works.
Keep checking in on this page as we will give updates at the project progresses!