“Testing” times at Hadnall school

We pride ourselves on working closely with our clients to ensure there’s minimal disruption to their day-to-day operation when we’re on site – and this also applies to exam season for our school projects.

So when Year 6 pupils at Hadnall Primary School were sitting their SATs recently, we happily changed our work programme to ‘quiet’ jobs that could be carried out while the children were doing their exams.

Work is progressing well on the school’s £360,000 extension that involves building a new classroom and enhancing the current teaching space, along with improvements to the reception and office and toilet facilities. It is on course to be completed by the start of the next school year in September.

 

This project is one of a number we’re currently delivering for Shropshire Council – we are also carrying out classroom extensions at Market Drayton Infants School; Market Drayton Junior School and St Andrew’s Primary in Shifnal.